ORGANIZATION WORK MGMT PROCESS:  FAQ 5 OF 10

5. How does PaSTA determine the availability of resources?

owm5.jpg

PaSTA has two ways to determine resources availability:

  1. Shift patterns can be imbedded within one another.  The definition of a shift pattern is the shortest amount of time before the pattern repeats; e.g. 4x10, 5x8 are 1 week patterns; “rolling 90” is an example of multiple week patterns.
  2. Resource leveling; PaSTA graphically shows the availability of individuals and/or craft to perform the work needed.